Athens Mayor Haris Doukas has sent a new letter to Infrastructure and Transport Minister Christos Dimas and Deputy Minister Nikos Tachiaos. In it, he asks for a new meeting with all the agencies involved and with representatives of the affected residents of Kypseli.

The letter focuses on four issues:

  • Dealing immediately with the danger posed by the buildings on Spetson Street.
  • Relocating the residents.
  • Completing the damage assessment reports.
  • Setting a clear timeline for the repair work and for restarting the tunnel boring for Metro Line 4.

The text of the letter follows:

“Ministers,

At a recent session of the Athens City Council, representatives of the residents of the affected apartment buildings in Kypseli referred to new information about how dangerous the buildings are, as well as to the continuing delay in completing repairs to the damage.

All of this means a constant lack of safety for the residents, which cannot under any circumstances continue.

We request a new meeting with the same parties that took part in the meeting of October 16, 2026: the Ministry, the City of Athens, the experts of the Technical Chamber of Greece (TEE), Hellenic Metro SA, the contractor consortium and the affected residents. The meeting would cover the following topics:

  • Urgent information about the ‘state of immediate danger’ identified by the contractor consortium in the buildings on Spetson Street, and about the work to remove it.
  • The specific plan for relocating residents for safety reasons and for the repair work.
  • The completion of the updated damage reports, and their release to the City and the residents. These reports follow the damage inspections carried out by a three-party team of engineers (the contractor, the TEE, and the residents with the City), as agreed at the meeting at the Ministry on October 16, 2026.
  • The release of a complete, overall timeline for all the affected apartment buildings. It should include the structural adequacy and repair studies in line with KANEPE, the Greek code for structural interventions, as well as the repair work itself, with completion set before the tunnel boring machine (TBM) resumes work.
  • Information on the timeline for restarting the tunnel boring work after the repairs are completed.

Ministers,

The repair work on the affected buildings in Kypseli must move forward properly, effectively, quickly and with full transparency.

On a major issue that concerns the very lives and property of residents, there must be trust and cooperation with the state and its agencies.

We look forward to the acceptance of our requests.

Sincerely,

Haris Doukas”